Fiber terminations left and we are done with the Fiber!!!!!

It's going to be a very very long weekend!!!

Helped pull in 3 Fiber feeds today and just a bit tired :( 

Up bright and early in the morning to get started.  Have to have 2 buildings online by Monday.  10 gigabit backbone connections here we come :)  Viewing the Roost couldn't be any faster once these buildings are done!

Title: Re: 264 more
Post by: Bulldogmikey on August 13, 2010, 09:36:59 PM
Maybe you will be back on cruise control soon!!
Title: Re: 264 more
Post by: M Sharpe on August 14, 2010, 05:29:10 AM
Porter, do you ever run into any Michels Communication guys? They do work for us down here in middle GA.
Title: Re: 264 more
Post by: Porter on August 15, 2010, 09:12:50 AM
Porter, do you ever run into any Michels Communication guys? They do work for us down here in middle GA.

No not a name I've heard up here.  There are about 6 to 8 companies here.  We've been with this one for about 6 years now.  Got all the fibers terminated yesterday and we are ready to get the building up and going!